CHG0125557- Nedbank planned maintenance

Scheduled for Jul 20, 00:01 - 07:00 SAST

Scheduled

The Nedbank technical team will carry out planned maintenance and a hardware refresh of the Outside Distribution Switches at Teraco Isando on Sunday, 20 July, from 00:01 to 07:00.

While connectivity interruptions are not expected, there may be brief blips during switch and firewall failovers. Application testers will be on site to perform pre-change checks, monitor the maintenance, and conduct post-change testing.

If you have any questions or concerns, please contact support@peachpayments.com or your account manager.
Posted Jul 16, 2025 - 14:14 SAST
This scheduled maintenance affects: Third-party Platforms (Nedbank card acquiring).