FNB Planned Maintenance

Scheduled Maintenance Report for Peach Payments

Completed

The scheduled maintenance has been completed.
Posted Oct 22, 2022 - 03:30 SAST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 22, 2022 - 03:01 SAST

Scheduled

In keeping with First Rand Group policy and requirements, The CJPIT BASE24, Postilion, FNB Switch and FNB eCommerce systems will shift processing to the Secondary Data Centre.
Due to this exercise, there will be intermittent transactional impact on the following days: -

Saturday 22nd October 2022 – Time 03:00 to 03:15.
Monday 24th October 2022 – Time 03:00 to 03:15.

Impacted Countries: -
South Africa
Lesotho
Eswatini
Namibia
Botswana
Zambia
Tanzania
Ghana
Guernsey
Posted Oct 21, 2022 - 18:04 SAST
This scheduled maintenance affected: Third-party Platforms (FNB card acquiring, Issuing systems for Card processing).